What is the usage of Period Factor?
—-
Period Factor maintained in the SNP PPM or Transportation Lane determines the Availability Date of a Receipt element within a time bucket (period). The system determines the exact availability date/time of the receipt elements within a period, by adding a time interval (that it gets by multiplying the period factor with the period length) to the start time of the period.
You can enter a factor between 0 and 1, where 0 is the start of the period, 0.5 the middle, and 1 the end of the period. When calculating the availability date/time, the system takes into consideration all weekdays, meaning that it does not take into consideration any days that have been defined as non-workdays in the calendars.