Regarding Call Horizon in the Maintenance Plan
If we create a Maintenance Plan with reference to a Package which has different cycles say (Weekly, Monthly, and Yearly). The call horizon is applied based on the least frequency.
For example:
If the call date is calculated as 3 days earlier for a Weekly cycle, it holds good for the monthly and Yearly cycle.
My client wants a different call horizon for each cycle defined in the Maintenance Package.
Is there any way to configure it as required by the client?
—
Answer
This is standard functionality. You can utilize user-exits to change these values.