Home › Forums › Plant Maintenance › Date used for Maintenance Plan Scheduling using Shift Factor
I need some confirmation information on Maintenance Plan Scheduling.
If you are using maintenance plan and makes use of Shift Factors, what date is used in the adjustment of the maintenance Plan which is considering previous order?
Is it the TECO date on the Order or is it on the Confirmations date?
I have heard it is on the first confirmed operation but cannot believe this, unless it is adjusted with every sub-sequent confirmation.
I do not have access to a system currently. Is there an explanation on the written principle to Plan Adjustments when using Shift Factors?
—
You know that really annoying pop-up box that appears when you TECO and order? The one with the reference date and time?
This is the information used as a basis for the shift factors. In the newer versions, there are two reference dates and times.
One of them is specifically used for maintenance plans.
The new functionality is available from version 4.7 onwards. You need to activate this for each of the maintenance plan category.