Home › Forums › Project System › Initial Screen of all PS Information System
In the initial screen of all PS Information system you can define the range of :
a) Project Definition
b) WBS Element
c) Network/Activities
d) Mile stone
e) The appearance of the initial screen depends on the database profile
Which are the correct answers?
—
In the initial screen of all PS Information system, you can define the range of project definition, WBS element, network/activities, and milestone. By defining the range, you can limit the data that will be displayed in the report. The appearance of the initial screen can also be affected by the database profile, but it is not one of the options for defining the range of data.
The correct answers are:
a) Project Definition
b) WBS Element
c) Network/Activities
d) Milestone