You understand by delegation in PS:
a) You can also set and remove deletion flags for WBS’s and networks manually.
b) Deletion indicators can not only be set in the background. Once set, they cannot be undone.
c) Residence times are set only for networks. They are defined in the network type.
Which are the correct answers?
—
Explanations
a) Delegation refers to the process of assigning responsibility for a specific task or element to another person or department. You have the ability to manually set and remove deletion flags for Work Breakdown Structures (WBS) and networks.
b) Once the deletion flag is set, it becomes permanent, and the system recognizes the object as flagged for deletion. Therefore, it’s crucial to be careful when setting deletion indicators, as they cannot be reversed once applied.
c) Residence times refer to the duration or period for which a network should exist or be valid. However, it’s important to note that residence times are applicable only to networks, not to other objects like WBS elements.
Correct answer a, c