You can create the following assembly orders:
a) Network
b) Production order
c) Planned order
d) Process order
e) Maintenance
f) Service order.
Which are the correct answers?
—
Explanations
Networks are basically an Object in SAP – Project system(PS). It is a special type of work order that has the same structure as production orders, maintenance orders, and inspection orders in the SAP System.
A production order is an order that contains all the necessary information for production, including the material requirements, production steps, and quality control checks. It is used to schedule and control the production of a product or service.
Planned order is used for generating procurement proposals or internal production requests. It represents the planned demand for materials or components required for a project or production. In SAP PS, you can create a planned order to initiate the procurement or production planning process based on the project’s requirements.
Process order is a type of order that is used to perform processes, such as painting or heat treatment. It specifies the quantity of products to be processed, the materials and labor required, and the process instructions.
Maintenance orders are used to schedule maintenance activities, such as preventive maintenance or corrective maintenance.
Planned orders are used to plan the production of goods or the provision of services, but they are not used to assemble products or services.
So, the correct answers are a), b), and d).