I keep receiving this message: “NO overlapping dates found”.
This message is not allowing me to save the project.
How can this be resolved?
—
You must be doing top-down scheduling. There must be inconsistencies in the dates of WBS and network activities. For that project to go through, correct them manually.
Also check the Planning board settings in Project profile configurations.
You might also want to check some OSS notes available for this message.