I am creating a recipe with material assignment with three finished products as the routing is same but BOMs are different.
How do I assign different BOMs in same recipe for different FERTs?
Is it possible or shall I create a separate recipe for all products?
—
Answer:
You will need to create a production version and link the different Alternative BOMs and recipes.