Checklist For Change of Material UOM

If you have already use that material, means purchase, produce or sell that item, it is not advisable to change Base UoM, but still if you need to know steps then:

1. Production Data: If it is a finished good or a component of a BOM, then remove BOM, remove assignment to Routing/Master Recipe, delete production versions. Delete any process/production orders or complete then and set status to TECO.

2. Purchasing: the deletion flag must be set in all current and old purchase orders and purchase info recs. Delete entries in source lists, contracts and outline agreements.

3. QM: Make UD on outstanding inspection lots.

4. Planning Data: Delete any forecasts or planned independent requirements or SOP/Flexible planning plans.

5. Sales: Cancel or complete the process for any sales documents (eg orders, deliveries). Remove or disable pricing records.

6. Warehouse Management: Cancel or complete transfer orders, transfer requirements, posting change notices. Ensure that no negative bin stock exists that cannot otherwise be balanced by other positive bin stocks.

7. Physical Inventory: Delete old, obsolete (but still active) physical inventory documents. Post Count, Adjust and close documents, or delete item from active documents.

8. Record previous period stock for the plant (MM03-Accounting). If non-zero then record details by batch and storage location (table MCHBH if using release > 4.0a).

9. You must remove previous period stock - the previous period in both MM and GL may need to be reopened (or wait until month-end processing when both previous and current periods are open simultaneously). To remove you need to use a transaction such as MI10 or MB1C and use a posting date of the previous period.

10. You must remove any remaining current period stock.

11. Planning Data (cont'd): delete all planned orders. Delete MRP List if any (check with MD05).

12. Costing: Delete any cost estimates.

13. Legacy Systems / Interfaces: Check what impact the change will have.

14. Material Master preparation:

* Ensure no alternative unit of measures are being used on the sales / purchasing / work scheduling / plant storage 1 views.

* Remove all alternative UoMs from "Extras"

15. CHANGE THE BASE UNIT OF MEASURE. If any errors, then check above steps again.

16. Material Master:

* Modify Planned Price 1, standard cost and/or moving average price on costing and accounting views.

* Modify any unit-related fields eg gross/net weights, MRP lot sizes / safety stock

* Re-create any alternative units of measure and re-assign to correct material master views.

17. Recovery: If you need any of the orders or master data deleted in any of the above steps, then now is the time.

18. Re-enter stock. Do not attempt to add back into previous period especially if using moving average price control (V) - do not back-date.

I think you would have change your opinion after reading all these steps, better is to create a new product.

SAP MM

Read also
Changing Base Unit Of Measure (Material Master)

SAP MM Reference Books:
SAP Material Management Interview Questions, Certification and Configuration Books

Goto:
SAP MM Purchasing

Back to:
SAP MM (Materials Management) Configuration Hints and Tips

Return to :-
SAP ABAP/4 Programming, Basis Administration, Configuration Hints and Tips

(c) www.gotothings.com All material on this site is Copyright.
Every effort is made to ensure the content integrity.  Information used on this site is at your own risk.
All product names are trademarks of their respective companies.  The site www.gotothings.com is in no way affiliated with SAP AG.
Any unauthorised copying or mirroring is prohibited.