How To Create Multiple Counter Plan

I  have to create multiple counter plan.  I  have created  cycle set for  every  20k miles and  every 12 month. What should be next?

Creating a Multiple Counter Plan :

Choose Logistics -> Plant Maintenance -> Preventive Maintenance -> Maintenance Planning -> Maintenance Plans -> Create -> Multiple Counter Plan.
You reach the initial screen for creating a maintenance plan.

-  Enter the necessary data:

-  Enter a maintenance plan category.
A maintenance plan category which generates service entry sheets for the due date, is not advisable for a multiple counter plan because the system would generate the same service entry sheet for each due date.  If you want to create the maintenance plan with a copy model for maintenance cycles, you enter a cycle set.

- Choose .
You reach the initial screen for creating a multiple counter plan.  Enter the necessary data for the maintenance plan header and create new maintenance cycles on the tabstrip Maintenance plan cycles or change/delete existing cycles if you have created the multiple counter plan with a cycle set as copy model.

-  Enter the necessary data for the maintenance item.
Assign a task list to the maintenance item:
- To assign an existing task list, choose.
- To create a task list, choose  with quick info Create Task List/ General Task List. Assign maintenance packages to the operations of the task list.

After you have assigned a task list, the system displays the following data:
-  The assigned task list on the Item tab page.
-  The maintenance packages from the strategy assigned to the operations in the task list on the Maintenance Plan: Cycles tab page.
-  Assign further technical objects to the maintenance item if necessary using the Object list (see Object List) tab page.
If you want to create further maintenance items, choose  with quick info Create MaintItem.
- Enter the necessary data, or select an unassigned maintenance item using .
- Assign a task list if necessary to each of the maintenance items.
- Assign other technical objects if necessary to the maintenance item.
In order to cancel the assignment of a maintenance item to the maintenance plan, choose.
- Maintain the scheduling parameters if necessary on the Maintenance Plan Scheduling Parameters tab page.
- Save the maintenance plan.

Then you should begin to input the measurement document.

I assume that you have created tasklists which you've attached inserted into the Maintenance Plan that you created and I also assume that you've picked the link to be either AND or OR.

Once those things are done, your deadline monitoring will of course begin to call the ORDERs or any other call object that you specified at the Maintenance Plan category.

By  :Olaoluwa Aaron Fapohunda

Read also :-
PM Notification Action Box

SAP Reference Books :-
SAP PM, CO, FI, PP, SD, MM, PS, QM, SM, HR, BW, APO, Basis,  ABAP/4, Certification, Books

Back to SAP PM :-
SAP PM (Plant Maintenance) Hints and Tips

Return to :-
SAP ABAP/4 Programming, Basis Administration, Configuration Hints and Tips

(c) www.gotothings.com All material on this site is Copyright.
Every effort is made to ensure the content integrity.  Information used on this site is at your own risk.
All product names are trademarks of their respective companies.  The site www.gotothings.com is in no way affiliated with SAP AG.
Any unauthorised copying or mirroring is prohibited.