I have to create multiple counter plan.
I have created cycle set for every 20k miles and
every 12 month. What should be next?
Creating a Multiple Counter Plan :
Choose Logistics -> Plant Maintenance -> Preventive Maintenance
-> Maintenance Planning -> Maintenance Plans -> Create -> Multiple Counter
Plan.
You reach the initial screen for creating a maintenance
plan.
- Enter the necessary data:
- Enter a maintenance plan category.
A maintenance plan category which generates service entry
sheets for the due date, is not advisable for a multiple counter plan because
the system would generate the same service entry sheet for each due date.
If you want to create the maintenance plan with a copy model for maintenance
cycles, you enter a cycle set.
- Choose .
You reach the initial screen for creating a multiple
counter plan. Enter the necessary data for the maintenance plan header
and create new maintenance cycles on the tabstrip Maintenance plan cycles
or change/delete existing cycles if you have created the multiple counter
plan with a cycle set as copy model.
- Enter the necessary data for the maintenance item.
Assign a task list to the maintenance item:
- To assign an existing task list, choose.
- To create a task list, choose with quick info
Create Task List/ General Task List. Assign maintenance packages to the
operations of the task list.
After you have assigned a task list, the system displays
the following data:
- The assigned task list on the Item tab page.
- The maintenance packages from the strategy assigned
to the operations in the task list on the Maintenance Plan: Cycles tab
page.
- Assign further technical objects to the maintenance
item if necessary using the Object list (see Object List) tab page.
If you want to create further maintenance items, choose
with quick info Create MaintItem.
- Enter the necessary data, or select an unassigned maintenance
item using .
- Assign a task list if necessary to each of the maintenance
items.
- Assign other technical objects if necessary to the
maintenance item.
In order to cancel the assignment of a maintenance item
to the maintenance plan, choose.
- Maintain the scheduling parameters if necessary on
the Maintenance Plan Scheduling Parameters tab page.
- Save the maintenance plan.
Then you should begin to input the measurement document.
I assume that you have created tasklists which you've
attached inserted into the Maintenance Plan that you created and I also
assume that you've picked the link to be either AND or OR.
Once those things are done, your deadline monitoring will
of course begin to call the ORDERs or any other call object that you specified
at the Maintenance Plan category.
By :Olaoluwa Aaron Fapohunda
Read also :-
PM
Notification Action Box
SAP Reference Books :-
SAP PM, CO, FI,
PP, SD, MM, PS, QM, SM, HR, BW, APO, Basis, ABAP/4, Certification,
Books
Back to SAP PM :-
SAP PM (Plant Maintenance)
Hints and Tips
Return to :-
SAP ABAP/4 Programming,
Basis Administration, Configuration Hints and Tips
(c) www.gotothings.com All material on this site is Copyright.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
All product names are trademarks of their respective
companies. The site www.gotothings.com is in no way affiliated with
SAP AG.
Any unauthorised copying or mirroring is prohibited.
|