Discrete mfg can be Make to stock / Make to order.
1) Make to stock :
Master datas :
Material master - MM01 - Strategy group
- 10 lot - ex
BoM - CS01
Routing - CA01
Wrk Centre - CR01
Creation of PIR - MD61
MRP RUN :- MD02 / MDBT in background
MD04 - STOCK LIST
CO41 - Conversion of planned orders
to production orders
CO05n - Release prodn orders
CO11N - Operation wise confirmation
Co15 - Header level confirmation.
MB31 - GR - assign auto gr thru control
key.
COHV - Mass techo the completed orders
Co88 / Ko88 - Settling the prodn orders.
2) Make to order :
Master data is the same in material
master maintain statergy as 20
Create a sale order - VA01
Run mrp - MD50 for sale order / md02
for material
MD04 - Stk requirement list
Rest all steps are same as mentioned
for make to stock.
Read Also:
What
Are Product Group
SAP PP Reference Books:
SAP
Production Planning , Configuration, Interview Questions and Certification,
Books
Goto:
SAP MRP -
Materials Requirements Planning Configuration Hints and Tips
Back to:
SAP PP (Production
Planning) Configuration Hints and Tips
Return to :-
SAP ABAP/4 Programming,
Basis Administration, Configuration Hints and Tips
(c) www.gotothings.com All material on this site is Copyright.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
All product names are trademarks of their respective
companies. The site www.gotothings.com is in no way affiliated with
SAP AG.
Any unauthorised copying or mirroring is prohibited.
|