Discrete Manufacturing Flow By Tcodes - A.Shankar

Discrete mfg can be Make to stock / Make to order.

1) Make to stock :

    Master datas :

    Material master - MM01 - Strategy group - 10 lot - ex
    BoM - CS01
    Routing - CA01
    Wrk Centre - CR01

    Creation of PIR - MD61
    MRP RUN :- MD02 / MDBT in background 
    MD04 - STOCK LIST
    CO41 - Conversion of planned orders to production orders
    CO05n - Release prodn orders
    CO11N - Operation wise confirmation Co15 - Header level confirmation.
    MB31 - GR - assign auto gr thru control key.
    COHV - Mass techo the completed orders
    Co88 / Ko88 - Settling the prodn orders.

2) Make to order :

    Master data is the same in material master maintain statergy as 20

    Create a sale order - VA01
    Run mrp - MD50 for sale order / md02 for material
    MD04 - Stk requirement list
    Rest all steps are same as mentioned for make to stock.

Read Also:
What Are Product Group

SAP PP Reference Books:
SAP Production Planning , Configuration, Interview Questions and Certification, Books

Goto:
SAP MRP - Materials Requirements Planning Configuration Hints and Tips 

Back to:
SAP PP (Production Planning) Configuration Hints and Tips

Return to :-
SAP ABAP/4 Programming, Basis Administration, Configuration Hints and Tips

(c) www.gotothings.com All material on this site is Copyright.
Every effort is made to ensure the content integrity.  Information used on this site is at your own risk.
All product names are trademarks of their respective companies.  The site www.gotothings.com is in no way affiliated with SAP AG.
Any unauthorised copying or mirroring is prohibited.