Individual Collective Indicator in the MRP 4 View

MRP 4 view in material master is for material that are listed as BOM of product or material or for material defined as dependent requirement.

Dependent requirement is affected when there are change in the Planned Independent Requirement (PIR).

When you choose 1 parameter,material requirements to buy will be generated when a customer order was entered under SD module (VA01).

On the other hand, parameter 2 like parameter 1 it is used in the BOM explosion of a product but in sales forecast basis (MD61).

To simplify, if material is unique or not common, with high value, with shelf life or short lead time, order proposals will be generated only during a customer order was received and entered in the system.

Choose parameter 1, you have better control to manage the stocks and values, parameter 2 is the reverse, when a material that is commonly used in many products that your company is producing. and when you planned product via forecast or sales plan basis then parameter 2 is your option to choose, if works when sales forecast of a product where the dependent requirement or material were being used it propose a buying proposals for the material requirement even though no receive or confirm customer order yet.

Read Also:
Control Regular Entry for Material Consumption

SAP PP Reference Books:
SAP Production Planning , Configuration, Interview Questions and Certification, Books

Goto:
SAP MRP - Materials Requirements Planning Configuration Hints and Tips 

Back to:
SAP PP (Production Planning) Configuration Hints and Tips

Return to :-
SAP ABAP/4 Programming, Basis Administration, Configuration Hints and Tips

(c) www.gotothings.com All material on this site is Copyright.
Every effort is made to ensure the content integrity.  Information used on this site is at your own risk.
All product names are trademarks of their respective companies.  The site www.gotothings.com is in no way affiliated with SAP AG.
Any unauthorised copying or mirroring is prohibited.