Purpose of Doing TECO For Production
Order
Technical Completion of a Production Order - Technical
completion means ending a production order from a logistical viewpoint.
This function is usually used, if the execution of an order has to be stopped
prematurely or if the order could not be executed in the required manner
and open requirements for the order (reservations, capacities) should be
deleted.
The Technically complete function must be allowed for
the operation, that is, it cannot be disallowed due to a system or user
status. To this end, the system checks the business transaction BTAB (technically
complete; see business transaction).
The following actions are executed if an order is set
to Technically complete.
-
The order is not relevant for MRP planning
-
Reservations are deleted
-
Capacity requirements are deleted
-
Purchase requisitions for external operations or non-stock
materials are deleted
-
The order and its operations receive the system status Technically
Completed (TECO)
-
If an order is technically complete, you cannot change it.
The fields in the order are displayed but cannot be changed. You can however
cancel technical completion, for instance if order data has to be changed.
If an order is technically complete, you cannot change it.
The fields in the order are displayed but cannot be changed. You can however
cancel technical completion, for instance if order data has to be changed.
After technical completion you can still make postings
for the order. For instance, material withdrawal or a confirmation can
be posted if they were previously forgotten. Activities You can execute
this function in two ways:
-
When you are changing an order, choose Functions --> Restrict
processing --> Technically complete.
-
Technically complete is a function that you can use in mass
processing.
You can reverse technical completion as follows:
When you are changing an order, choose Functions -->
Restrict processing --> Revoke technical completion.
Read Also:
SAP
PP Configuration Tcodes
SAP PP Reference Books:
SAP
Production Planning , Configuration, Interview Questions and Certification,
Books
Goto:
SAP MRP -
Materials Requirements Planning Configuration Hints and Tips
Back to:
SAP PP (Production
Planning) Configuration Hints and Tips
Return to :-
SAP ABAP/4 Programming,
Basis Administration, Configuration Hints and Tips
(c) www.gotothings.com All material on this site is Copyright.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
All product names are trademarks of their respective
companies. The site www.gotothings.com is in no way affiliated with
SAP AG.
Any unauthorised copying or mirroring is prohibited.
|