The Subcon Process in SAP Purchasing
Modules
What
are the Subcontract Processes?
Subcontracting Processing
When a main BOM item is a subcontract item (in the item
category field of PO/PR line item, the value is "L"), then the system will
automatically know that the sub items need to be issued out. Such
issue, from the internal system processing view point, is only a transfer
from one storage location to the subcontractor vendor storage location
rather than a consumption. It will only be deemed a consumption when
the parent item is received back from the vendor. The system will
automatically track all the items sent to the vendor waiting to be receieved
back.
The following are the pre-requisite procedure for handling
subcontract items:
-
When setting up the subcontracted parent item (material type
HALB), the material master has a procurement type of "F" and special procurement
of 30. The effect is that when the purchase requistion was created
by MRP or manually, the item category will be "L".
-
BOM items for the main part has been setup to contain all
the materials which must be supplied FOC to the vendor.
-
There is no need to setup the routing for the sub-contracted
main item.
The following are subcontracted related procedures:
-
Finding out what sub-items need to be issued to subcontractors
and issue them.
-
Finding out what sub-items have been issued to subcontractors
and waiting to come back.
-
Receiving subcontracting item (from the store viewpoint,
there is no difference from normal receiving).
-
Invoice processing : the invoice is only for the services
and is no difference from normal processing.
Invoke transaction ME2O
-
Leave the Date required, Material and Plant blank unless
you wish to limit the listing to a specific area. Check the Only
Negative available SC stocks if you only want to look at the cases where
materials need to be handed to the subcontractor. If you do not check
this, then items which have already been issued to the subcontractor and
waiting to come back will also be shown.
-
To issue the items to the subcontractor, select the item,
then click Post goods issue button.
-
Enter the storage location from which the sub-items is taken
out, and the quantity given.
-
If there is not sufficient on hand stock to be given to the
subcontractor, then the system will issue a "0 items posted" message.
If there is sufficient quantity, the system will transfer the quantity
to the vendor storage location. On this screen, you can also check
the on hand stock balance by clicking the stock overview and stock/requirement
buttons. You may also palce the cursor on a PO number and display
the PO details giving rise to this SC issuing requirement.
Subcontract Posting
Material Document
101 +
Receive in the new Material after sub-contract
543 -
Clear the quantity in Material Provision for Vendor
Accounting Document
Debit Inventory - New Part
150
Credit Inventory - Purchase Offset
150
Debit Service cost for sub-contract
50
Credit GR/IR - Inventory
50
Debit ROH - Material Consumed
100
Credit ROH - Material Consumed
100
SAP MM Reference Books:
SAP Material
Management Interview Questions, Certification and Configuration Books
Goto:
SAP MM Purchasing
Back to:
SAP MM (Materials Management)
Configuration Hints and Tips
Return to :-
SAP ABAP/4 Programming,
Basis Administration, Configuration Hints and Tips
(c) www.gotothings.com All material on this site is Copyright.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
All product names are trademarks of their respective
companies. The site www.gotothings.com is in no way affiliated with
SAP AG.
Any unauthorised copying or mirroring is prohibited.
|