Question :
When I create an operation with
control key PM02, external process, why I cannot generate a purchase requisition?
Does the requisition screen pop
up or not at all?
If it does, are all the fields
on the requisition field visible?
The requistion screen was not showed
at all. I don't know how to generate the PR with control key PM02.
Is there any confirguation on background?
Answer :
Try settings in T-Code ;OIO7 fields
ext processing and Service
Check:
- in the control key PM02 that the
field External operation has the symbol "+" as in Standard SAP
- in the Tx OIOE, that the link
Plant - Order Type has the field "Purchase Requisition" --> Inmediately
Task
List Transfer
Question :
When copy task list to order,it should realize according
to SAP 's description:"you can make settings in Customizing so that a dialog
box appears when you include a task list in an order.
This dialog box enables you to choose operations, change
the work center and set execution factors.".But I don't know where to set
the customizing.
Answer :
I normally copy all task list data by using Customizing:
PM
--> Maintenance / Service Processing
--> --> Maintenance & Service Orders
--> --> --> Functions & Settings for Order Types
--> --> --> --> Default Values for task Lists Data &
Profile Assignment
you could manage this screen for selection
SAP Reference Books :-
SAP PM, CO, FI, PP,
SD, MM, PS, QM, SM, HR, BW, APO, Basis, ABAP/4, Certification, Books
Back to SAP PM :-
SAP PM (Plant Maintenance)
Hints and Tips
Return to :-
SAP ABAP/4 Programming,
Basis Administration, Configuration Hints and Tips
(c) www.gotothings.com All material on this site is Copyright.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
All product names are trademarks of their respective
companies. The site www.gotothings.com is in no way affiliated with
SAP AG.
Any unauthorised copying or mirroring is prohibited.
|