Configuring an Additional Activity
Type
Additional Activities Type for Work Center
The following are the steps to configure an additional
activities type:-
-
OP51 - Check Settings for formulas
-
OP54 - Check formulas for Costing
-
Ensure that usage of the parameters are indicated.
Some parameters are appropriate for capacity calculation but not for schedule
calculation. If you like to find out the parameter id, you could
use the Search Fld. for Param. pull down button to do so.
-
KLH2 - Maintain hierarchy of Activity type group.
-
OP19 - Define standard value key
-
The purpose of standard value keys is to group together a
set of parameters for the purpose of ensuring that the standard values
for the parameters are supplied in the operations of the routing.
This is so that the formula (for calculating cost, schedule, and capacity)
could have the necessary figures to work with. Once the parameters
are associated with the standard value keys, work centers quoting this
standard values will be able to dictate whether or not the parameter values
are optional or mandatory entry in the operations of the routing.
The pre-requisite for using this transaction is that the parameters must
have been pre-created.
-
KA01 - Create Primary Cost Element for the new activities
type.
-
KL01 - Create Activity Type tied to the primary
cost element. (the
Cost element field)
-
KP26 - Change Activity Type/Activity Price Planning
- maintain the Variable price
If the user include the additional activities in their work
center, the routing that used the work center will required more time to
finished the jobs.
The operations Start and Finish date will be extended
due to the extra time spent on the work center. The cost of production
increases in line with the extra activity which will be reflected in the
Factory Output when you do a cost analysis in the production order.
The new activity will have a price attached to it and the moving average
price will increase.
SAP PP Reference Books:
SAP
Production Planning , Configuration, Interview Questions and Certification,
Books
Goto:
SAP MRP - Materials
Requirements Planning Configuration Hints and Tips
Back to:
SAP PP (Production
Planning) Configuration Hints and Tips
Return to :-
SAP ABAP/4 Programming,
Basis Administration, Configuration Hints and Tips
(c) www.gotothings.com All material on this site is Copyright.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
All product names are trademarks of their respective
companies. The site www.gotothings.com is in no way affiliated with
SAP AG.
Any unauthorised copying or mirroring is prohibited.
|