Total Plan Activities in Minutes
afru
-> Order completion confirmations
afru-smeng -> Operations qty
afvv
-> DB structure of the quantities/dates/values in the operation
afvv-bmsch -> Base quantity
afvv-vgw01 -> Standard value for Direct Labour
afvv-vgw02 -> Standard value for Setup
afvv-vgw03 -> Standard value for Machine Time
afvv-vgw04 -> Standard value for Adjustment of Tool
Formula
Direct Labour
= ( afru-smeng / afvv-bmsch ) * afvv-vgw01 * 60.
Setup
= afvv-vgw02 * 60.
Machine Time
= ( afru-smeng / afvv-bmsch ) * afvv-vgw03 * 60.
Adjustment of Tool = afvv-vgw04
* 60.
Formula
CR03 - Display Work Center
At CR03, click Assignments.
Then double click on the Cost Center.
Place your cursor at the Activity
type, click Extra -> Formula -> Display.
SAP PP Reference Books:
SAP
Production Planning , Configuration, Interview Questions and Certification,
Books
Goto:
SAP MRP - Materials
Requirements Planning Configuration Hints and Tips
Back to:
SAP PP (Production
Planning) Configuration Hints and Tips
Return to :-
SAP ABAP/4 Programming,
Basis Administration, Configuration Hints and Tips
(c) www.gotothings.com All material on this site is Copyright.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
All product names are trademarks of their respective
companies. The site www.gotothings.com is in no way affiliated with
SAP AG.
Any unauthorised copying or mirroring is prohibited.
|