Change Production Order - CO02
4.6c
Msg C7038 - Schedule conflict:Constraint
is too late
In the order XXXXXX the operation 80 and 90 are partially
confirmed with the following actual date:
Operation 80 actual start: 24.07.XXXX
21:39.23
Operation 90 actual start: 26.07.XXXX
07:22.15
For the partiall confirmed operation, the remaining duration
is scheduled after the confirmed atual date. This mean, that the program
schedule for the operations 80 and 90 forward, even though "backward- scheduling"
is set for the order.
The program calculate that the operation should finish
at 26.07.XXXX 12:35.49, it is greater than the actual start date
of the
operation 90 26.07.XXXX 07:22.15. And the operation
90 is the successor of the operation 80. So is the actual date of the operation
80 (24.07.XXXX 21:39.23) too late, this constraint is the cause of the
conflict.
You can set the scheduling indicator "shift order", and
you can get rid of this problem.
CO02 - Order -> Settings
- Scheduling parameters -> Tick Shift order
Default for all newly created orders.
(Plant dependant)
OPU3 - Define Scheduling
Parameters for Production Orders.
SAP PP Reference Books:
SAP
Production Planning , Configuration, Interview Questions and Certification,
Books
Goto:
SAP MRP - Materials
Requirements Planning Configuration Hints and Tips
Back to:
SAP PP (Production
Planning) Configuration Hints and Tips
Return to :-
SAP ABAP/4 Programming,
Basis Administration, Configuration Hints and Tips
(c) www.gotothings.com All material on this site is Copyright.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
All product names are trademarks of their respective
companies. The site www.gotothings.com is in no way affiliated with
SAP AG.
Any unauthorised copying or mirroring is prohibited.
|