Basic dates history in production
order
Hi,
There is a table where are recorded modification to basic
dates in production order?
Thanks
Answer : Subject : Basic dates history in production order
Hi,
Is that PLAF that you means?It contains basic date and
quanity for a planned order.
Regards.
Answer : Subject : Basic dates history in production order
Hello,
For a production order, basic dates are available in AFKO
table..
But, it looks like you are looking for the history of
all the changes made to the basic dates.
Please check table HIKO. I think you will have to go
for order change management (OCM) for that. We donot have OCM here and
HIKO table is empty. Please let me know if it is correct..
Regards
Answer : Subject : Basic dates history in production order
Hi,
I've checked : also our HIKO is empty and in effect OCM
has not been implemented.
Thank you very much for your help.
Regards
SAP PP Reference Books:
SAP
Production Planning , Configuration, Interview Questions and Certification,
Books
Goto:
SAP MRP - Materials
Requirements Planning Configuration Hints and Tips
Back to:
SAP PP (Production
Planning) Configuration Hints and Tips
Return to :-
SAP ABAP/4 Programming,
Basis Administration, Configuration Hints and Tips
(c) www.gotothings.com All material on this site is Copyright.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
All product names are trademarks of their respective
companies. The site www.gotothings.com is in no way affiliated with
SAP AG.
Any unauthorised copying or mirroring is prohibited.
|