MD02 - Run MRP Single item Multi level

MRP reads the requirement from:

  • Material Master View
    • Purchasing
    • MRP 1 and 2
    • Work Scheduling
  • Sales Order
  • Planned Independent Requirement
  • BOM
  • Routing
Points to note:-
If you have just changed the BOM and want to have the latest update.
Execute with Planning Mode    2  -  BOM is re-exploded

When you found that the MRP did not automatically Create the Purchase Requisitions for in-house production.
Execute with Planning Mode    3  -  Delete planning dates.

MRP can easily re-create Purchase Requistions and Planned Orders based on the latest requirement changes.  Therefore, it is allright to execute with Planning Mode 3.

BOM - Do not built a BOM with a Material Type ROH Level 1 and Level 2, as MRP will not consider the requirement for Level 2 since it is a Raw Material.  (no additional process required).

                        Level  1        ROH

                         ...Level 2        ROH

SAP PP Reference Books:
SAP Production Planning , Configuration, Interview Questions and Certification, Books

Goto:
SAP MRP - Materials Requirements Planning Configuration Hints and Tips 

Back to:
SAP PP (Production Planning) Configuration Hints and Tips

Return to :-
SAP ABAP/4 Programming, Basis Administration, Configuration Hints and Tips

(c) www.gotothings.com All material on this site is Copyright.
Every effort is made to ensure the content integrity.  Information used on this site is at your own risk.
All product names are trademarks of their respective companies.  The site www.gotothings.com is in no way affiliated with SAP AG.
Any unauthorised copying or mirroring is prohibited.