Shortage/Surplus of material stock level due to differences in Planned/Production Order Start and Finish date

Normally, the planned order determined the date from Material Master.  The Planned Order created by the MRP reads the production capacity requirement from Material Master. (MM03 – Work Scheduling – Lot size dependent in-house production time).  When you convert the planned order to a production order, SAP determined the date from Routing.

User Requirements:-  Planned and Production Order should read the requirement from routing.

Solutions:-
Run MRP Scheduling -> 2 – Lead time scheduling and capacity planning

Transaction OPA9 (Sel. Profile - SAPA010) - Change configuration for Capacity Planning to read Production Order.  Untick the Planned orders under the Order categories.

SAP PP Reference Books:
SAP Production Planning , Configuration, Interview Questions and Certification, Books

Goto:
SAP MRP - Materials Requirements Planning Configuration Hints and Tips 

Back to:
SAP PP (Production Planning) Configuration Hints and Tips

Return to :-
SAP ABAP/4 Programming, Basis Administration, Configuration Hints and Tips

(c) www.gotothings.com All material on this site is Copyright.
Every effort is made to ensure the content integrity.  Information used on this site is at your own risk.
All product names are trademarks of their respective companies.  The site www.gotothings.com is in no way affiliated with SAP AG.
Any unauthorised copying or mirroring is prohibited.