Quota Arrangement for Multi
Plant Purhasing
If you have more than two Plant, you can used quota arrangement
to distribute the percentage of internal purchasing accordingly.
Plant A purchase from Plant B Plant C
MM02 - Procurement
type F
Special procurement Blank
Quota arr.usage
3
Plant B and Plant C
MM02 - Procurement
type F
Special procurement Blank
Quota arr.usage
Blank
OMD9 - Maintain Special
Procurement
Plnt SP Type
Special Procurement type description
Plant A Plant B Procure from
Plant B
Plant A Plant C Procure from
Plant C
MEQ1 - Quota Arrangement
for Plant A
If you press Enter, the start date comes automatically.
Multiple period can be maintained.
Click Item Overview for Overview of Quota items
P S PPl.
Quota
F U Plant B
30
F U Plant C
70
P - Procurement type
S - Special Procurement
SAP PP Reference Books:
SAP
Production Planning , Configuration, Interview Questions and Certification,
Books
Goto:
SAP MRP - Materials
Requirements Planning Configuration Hints and Tips
Back to:
SAP PP (Production
Planning) Configuration Hints and Tips
Return to :-
SAP ABAP/4 Programming,
Basis Administration, Configuration Hints and Tips
(c) www.gotothings.com All material on this site is Copyright.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
All product names are trademarks of their respective
companies. The site www.gotothings.com is in no way affiliated with
SAP AG.
Any unauthorised copying or mirroring is prohibited.
|