Connecting the planning calendar
to your lot size key
First, you will need to set up the planning calendar.
Menu path: Production -> MRP
-> Master Data -> Planning Calendar (MD25)
You will then need to use this planning calendar (the
one you created) in the material master when planning your raw materials
(MRP2 View in 4.6C - Field name : Planning Calendar).
1. When you maintain the planning calendar you will need
to enter a valid from date and valid to date.
2. Your periods will also need to be set up and they will
be weekly, for example:
From Date
: 11/23/2001 To Date
: 11/29/2001 (11/23 is a Friday, this is your from
date).
Do this for as may weeks as you wish
(say weekly for 2 years).
3. When you have set up the planning calendar, you will
then need to make some changes to the weekly lot size configuration
(WB), or you may need to create a
new lot size key if you do not want to change 'WB'. Essentially, you will
need to use the
following in the lot size configuration
(OMI4) :
No. of Periods : 1
LotSizeProced.: P
LotSize ind : K
Scheduling : 1
By using the above, you are connecting the planning calendar
to your lot size key.
SAP PP Reference Books:
SAP
Production Planning , Configuration, Interview Questions and Certification,
Books
Goto:
SAP MRP - Materials
Requirements Planning Configuration Hints and Tips
Back to:
SAP PP (Production
Planning) Configuration Hints and Tips
Return to :-
SAP ABAP/4 Programming,
Basis Administration, Configuration Hints and Tips
(c) www.gotothings.com All material on this site is Copyright.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
All product names are trademarks of their respective
companies. The site www.gotothings.com is in no way affiliated with
SAP AG.
Any unauthorised copying or mirroring is prohibited.
|