Is there a status that can be set for a network activity that will stop time confirmations from being processed? TECO stops changes to the basic data, but allows further time confirmations.

TIA
 

Reply : Subject : PS Network Status's & Confirmations

hi...

You can lock account assignment for the network/activity in consideration depending on whether the network is header/activity
assigned. This disallows the confirmation of the activities.

...else you can use the user status

regards...

SAP PS Reference Books:
SAP Project System, Interview Questions and Certification, Books

Back to SAP PS Main Menu:
SAP PS (Project System) Hints and Tips

Return to :-
SAP ABAP/4 Programming, Basis Administration, Configuration Hints and Tips

(c) www.gotothings.com All material on this site is Copyright.
Every effort is made to ensure the content integrity.  Information used on this site is at your own risk.
All product names are trademarks of their respective companies.  The site www.gotothings.com is in no way affiliated with SAP AG.
Any unauthorised copying or mirroring is prohibited.