PS Network Status's & Confirmations
Sappers: Is there a status that can be set for a network activity that will stop time confirmations from being processed? TECO stops changes to the basic data, but allows further time confirmations. TIA
Reply : Subject : PS Network Status's & Confirmations hi... You can lock account assignment
for the network/activity in consideration depending on whether the network
is header/activity
...else you can use the user status regards...