Material Requirement Planning Multipe Choice Questions And Answers #1

1) For Planning Material Requirements with Requirements Grouping. The following options are available:

A. Automatic Requirements Grouping Within a Project
B. Multi-Plant Requirements Grouping with a Grouping WBS Element
C. Multi-Plant Requirements Grouping with Several Grouping WBS Elements
D. Requirements Grouping with a Grouping WBS Element for Each Plant
E. Requirements Grouping with Several Grouping WBS Elements for Each Plant
F. Requirements Grouping with Hierarchically Structured Grouping WBS Elements
 

2) The following evaluations are available for analyzing the planning result:

A. MRP list
B. stock/requirements list
C. planning result (corresponds to the MRP list with individual evaluation layout)
D. planning situation (corresponds to the stock/requirements list with individual evaluation layout)
E. planning table for repetitive manufacturing
 

3) The MRP procedures supported in consumption-based planning are:

A. Reorder Point Planning
B. Forecast-Based Planning
C. Time-phased planning
 

4) The master data for MRP, which can be maintained over the MRP menu, includes:

A. planning calendar
B. quota arrangements
C. BOM explosion number
 

5) Distribution resource planning provides a framework for determining the need to replenish inventory by:

A. Linking market requirements with manufacturing and demand management
B. Relating current inventory positions and demand forecasts to production scheduling
C. Matching material supply to manufacturing demand, and customer demand to product supply
 

6) In order to perform a DRP run, you must:

A. Set up a distribution network, including identification of quota arrangements and lead times.
B. Define MRP parameters in the material master record for all the materials in the distribution network.
 

7) The deployment results, displayed after the deployment run, indicate:

A. Quantities to be deployed to each DC from the specified supplying plant
B. Delivery dates
C. Additional information used by the system to determine the deployment
 

8) You specify a fair share rule in the MRP 4 view of the material master record to identify how you want fair share to be implemented:

A. Fair share rule A distributes the stock proportionally to all DCs according to demand.
B. Fair share rule B is raises the stock levels in all DCs to approximately the same percentage of target stock level.
 

9) If you have assigned an MRP profile and/or forecast profile to a material, it may later be necessary to:

A. Delete the assignment of the profile to the material if you want to overwrite the fixed values defined in the profile
B. Assign the material to a different profile
 

10) There are two types of availability check:

A. Availability check for the various stock types in Inventory Management
B. Check for the available stocks in Materials Planning (MRP)
C. None of above

---

Correct Answers

1) A, B, C, D

2) A, B, C, D

3) A, B, C

4) A, B, C

5) A, B, C

6) A, B

7) A, B, C

8) A, B

9) A, B

10) A, B

SAP MRP

Read Also:
Materials Requirement Planning Self-Test Knowledge

SAP PP Reference Books:
SAP Production Planning , Configuration, Interview Questions and Certification, Books

Goto:
SAP MRP - Materials Requirements Planning Configuration Hints and Tips 

Back to:
SAP PP (Production Planning) Configuration Hints and Tips

Return to :-
SAP ABAP/4 Programming, Basis Administration, Configuration Hints and Tips

(c) www.gotothings.com All material on this site is Copyright.
Every effort is made to ensure the content integrity.  Information used on this site is at your own risk.
All product names are trademarks of their respective companies.  The site www.gotothings.com is in no way affiliated with SAP AG.
Any unauthorised copying or mirroring is prohibited.