Explain the complete process / procedure of Long Term
Planning (LTP).
Answer: For Long term Planning, use T.code : MD61 to create the Planned Independent Requirement for Month wise. Planning for the year or as per your requirement. Transaction code: MD61 Provide material name Provide Plant name Requirement Type : BSF ( Gross Requirement), LSF ( Net Requirement) as per your business requirement Planning Version Planning Horoizon : From To ..Planning Period Enter Fill Month wise / Day wise plan as chosen Save If you want to activate your planning, then tick the version
active. If after creating the LTP , you want to do the stimulation, then
make the version inactive. After stimulation run, once the planning version
is firmed go to change mode i.e. MD62 & activate the concerned version.
How to delete Plan created from MD61 Answer: If you want to delete plans created in MD61 use transactions md74 - reorganizing indep.reqmts - adjusting requirements md75 - indep.requirements reorganisation - delete old requirements records md76 - reorg.indep.reqmnts - delete history and independent requirements |
|
Read Also:
SAP PP Reference Books:
Goto:
Back to:
Return to :-
(c) www.gotothings.com All material on this site is Copyright.
|